Backward Schedule (Is it possible?)
Backward Schedule (Is it possible?)
(OP)
I am having a problem with the following:
Engineering
Task 1
Procurement
Task 2
Task 1 will start after Task 2 is complete. I would like to create a sort of backward FS (Task2>Task1). Question: Is this possible w/o moving Task 1 below Task 2 and creating a FS relationship. Moving Task 1 below Task 2 would create a problem with the layout (presentation) of the schedule.
Any help with this would be greatly appreciated.
Regards
Engineering
Task 1
Procurement
Task 2
Task 1 will start after Task 2 is complete. I would like to create a sort of backward FS (Task2>Task1). Question: Is this possible w/o moving Task 1 below Task 2 and creating a FS relationship. Moving Task 1 below Task 2 would create a problem with the layout (presentation) of the schedule.
Any help with this would be greatly appreciated.
Regards
RE: Backward Schedule (Is it possible?)
MSP doesn't care what order the tasks are laid out relative to the predecessor/successor relationship.
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
RE: Backward Schedule (Is it possible?)
I have tried this in the past and was unsuccessful.
To be more specific:
1.0 Engineering
Complete As built Drawings (15days) “start date to be determined by relationship”
2.0 Commissioning
Commission Plant #1 (10 days) Mar 01 to Mar 05
Commission Plant #2 (10 days) Mar 20 to Mar 30
Commission Plant #3 (10 days) June 30 to July 20
I would like to present the above as is on the schedule. I do not want to put the Engineering summary underneath the Commissioning summary.
As it stands now, as built drawings can only start after the last commissioning task (i.e. in this case Commission Plant #3) which would begin on July 21 and take 10 days to complete.
When I try to complete a FS relationship between C. Plant #3 and C. As built drawings the relationship shows the link arrow from Complete As built drawings to Complete Plant #3 rather than the other way around.
If this relationship is possible: Is it possible to link all commissioning activities to the Complete As built drawings so by default the Complete As built drawings would start after the finish of the last commissioning activity. This would be important during the project if Plant #1 became the last commissioning activity as opposed to Plant #3 OR is this something that the planner has to manually adjust if the sequence of activity changes
RE: Backward Schedule (Is it possible?)
If last commision is line 10 and drawing is line 4, then line 4 should have 10FS in predecessor. Works every time.
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
RE: Backward Schedule (Is it possible?)