×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Backward Schedule (Is it possible?)

Backward Schedule (Is it possible?)

Backward Schedule (Is it possible?)

(OP)
I am having a problem with the following:

Engineering
    Task 1
Procurement
    Task 2


Task 1 will start after Task 2 is complete.  I would like to create a sort of backward FS (Task2>Task1). Question:   Is this possible w/o moving Task 1 below Task 2 and creating a FS relationship.  Moving Task 1 below Task 2 would create a problem with the layout (presentation) of the schedule.

Any help with this would be greatly appreciated.

Regards
Replies continue below

Recommended for you

RE: Backward Schedule (Is it possible?)

Why didn't you just try it?  

MSP doesn't care what order the tasks are laid out relative to the predecessor/successor relationship.

TTFN

FAQ731-376: Eng-Tips.com Forum Policies

RE: Backward Schedule (Is it possible?)

(OP)
Thanks.

I have tried this in the past and was unsuccessful.

To be more specific:

1.0 Engineering
  Complete As built Drawings (15days) “start date to be determined by relationship”

2.0 Commissioning
  Commission Plant #1 (10 days) Mar 01 to Mar 05
  Commission Plant #2 (10 days) Mar 20 to Mar 30
  Commission Plant #3 (10 days) June 30 to July 20

I would like to present the above as is on the schedule.  I do not want to put the Engineering summary underneath the Commissioning summary.

As it stands now, as built drawings can only start after the last commissioning task (i.e. in this case Commission Plant #3) which would begin on July 21 and take 10 days to complete.

When I try to complete a FS relationship between C. Plant #3 and C. As built drawings the relationship shows the link arrow from Complete As built drawings to Complete Plant #3 rather than the other way around.

If this relationship is possible:  Is it possible to link all commissioning activities to the Complete As built drawings so by default the Complete As built drawings would start after the finish of the last commissioning activity.  This would be important during the project if Plant #1 became  the last commissioning activity as opposed to Plant #3 OR is this something that the planner has to manually adjust if the sequence of activity changes

RE: Backward Schedule (Is it possible?)

The relationship is possible.  You're doing something wrong.

If last commision is line 10 and drawing is line 4, then line 4 should have 10FS in predecessor.  Works every time.

TTFN

FAQ731-376: Eng-Tips.com Forum Policies

RE: Backward Schedule (Is it possible?)

(OP)
Thank you very much for help.  It worked great but I had to manually type the 10FS relationship in the predecessor text box.  Is there a way to use the FS button to establish this relationship?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close