Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Oil Flush for Lube Oil System

Status
Not open for further replies.

StartMeUp

Civil/Environmental
Apr 10, 2002
1
Is there a rule of thumb to calculate flow requirements (i.e. velocity or flow rate) for initial flushing of lube oil piping for large rotating equipment (ID Fans for a large boiler)? The installation will consist of 2" and 3 " field welded stainless piping. The need is to provide sufficent velocity to remove any "heavy" particulate from the piping.
 
Replies continue below

Recommended for you

Startmeup,

Will you be using the circulation pumps from the new system or temporary pumps just for flushing ?

Based on the rule of thumb for boiler circulation and initial flush, if you can circulate at the design flow rate or better, you have it made.

Will you be using a "flushing liquid" that has a significantly different specific gravity than the operating liquid ? If so you may have to flush at a higher rate to ensure cleanliness.

You will, of course, be using temporary strainers/screens to catch particulate ?

MJC
 
You should try to keep the Reynolds number above 4000 during your flushing operation. You can calculate this as follows:

Nr = 3160 * GPM / (ViscosityCst * IDinches) or

Since the viscosity of oils changes so markedly with temperature it is difficult to give a simple, general "Rule of Thumb".

Regards,
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor