INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Time of Concetration

Time of Concetration

Time of Concetration

(OP)
I have always been a bit confused as to how to develop a proposed Time of Concetration in which to model detention. Most of the work my firm does are small (~5 acres commercial sites). Most time of concetration models assume all water is channeled directly to the pond. For instance, TR-55 assumes sheet flow, shallow concentrated, and channelized. This is easy to figue in an undeveloped state.

However, in a proposed commercial site, water will sheet flow to the storm sewer. The inlets and pipe are generally designed for the 10 year event. In the 100 year event, water will pond above the inlets and flow to the detention basin through overland flow routing. So to get a time of concetraion for the 100 year event is almost impossible. Does it make sence to use the final time of the 10 year storm sewer to model the detention?

I guess, I usually see engineers state that they used the TR-55, LAG, or some other equation to get a Time of Concetration to model their detention. But in a developed state, I do not see how that is possible.

RE: Time of Concetration

Detention/retention is designed for a specific return interval storm.  Use the time for the design storm; an estimate of overland flow time can be calculated and the total will probably be similar,(120% to 200%), to the 25 year time.

RE: Time of Concetration

Remember, these are models and many approximations are made in an attempt to come up with a "scenario" that will encompass natural events which will NEVER look exactly like synthetic models.  

You state that water will pond above all inlets in the 100 year event.  This will not happen the instant rainfall starts.  Tc will be valid until the flooding does occur.  

If you are truly concerned about the effects of ponding in the paved areas, you should model them accordingly.  In the work I have done on similar sites, I am not concerned about water ponding on the paving during a 100 yr event and it probably has little effect on a small site.  On a "big box" store site, with vast parking areas, the ponding may provide storage and the stormater facility is oversized if the storage is ignored (chalk it up as a safety factor?)

RE: Time of Concetration

I always compute the Tc in the following manner:

Leg 1: Sheet flow across lawn/landscaping for 50 ft or so (or the actual distance, if less) with a Manning's n value of 0.15

Leg 2: Shallow concentrated flow over lawn/landscaping (unpaved) surface, if applicable

Leg 3: Shallow concentrated flow across the parking lot paving to the storm sewer inlet

Leg 4: Channelized flow within the storm sewer until it reaches the basin

Once you reach the basin - Tc ends

RE: Time of Concetration

(OP)
So your Tc for your pond would be about what the final Tc for the storm sewer system is?

RE: Time of Concetration

The Tc is for the basin inflow hydrograph (in this case, the storm sewer directing flow to the basin).  There is no 'pond' Tc.  Rather, the inflow hydrograph gets routed through the pond, which, depending upon the basin control configuration, determines the basin discharge rates and draw-down time.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

Low-Volume Rapid Injection Molding With 3D Printed Molds
Learn methods and guidelines for using stereolithography (SLA) 3D printed molds in the injection molding process to lower costs and lead time. Discover how this hybrid manufacturing process enables on-demand mold fabrication to quickly produce small batches of thermoplastic parts. Download Now
Design for Additive Manufacturing (DfAM)
Examine how the principles of DfAM upend many of the long-standing rules around manufacturability - allowing engineers and designers to place a part’s function at the center of their design considerations. Download Now
Taking Control of Engineering Documents
This ebook covers tips for creating and managing workflows, security best practices and protection of intellectual property, Cloud vs. on-premise software solutions, CAD file management, compliance, and more. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close