Resource Usage Reporting by Summary
Resource Usage Reporting by Summary
(OP)
I see an old question about this with no replies. Does anyone have any way to report on Resources by project rather than by task?
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS Contact USThanks. We have received your request and will respond promptly. Come Join Us!Are you an
Engineering professional? Join Eng-Tips Forums!
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail. Posting Guidelines |
Resource Usage Reporting by Summary
|
Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.
Here's Why Members Love Eng-Tips Forums:
Register now while it's still free!
Already a member? Close this window and log in.
RE: Resource Usage Reporting by Summary
-Click on >View, >Resource Sheet
-Click on >Window, >Split
-Click anywhere in the bottom pane, the click on >View, >Resource Graph
-Now by clicking on the various resource names in the top pane, you will get to see their allocation in graphical format in the bottom pane.
Tweaking the view:
1. You may want to change the timephased view in the graph. I prefer to examine resource allocations at a month period. To change the time period:
-Click anywhere in the bottom pane
-Click on the Zoom Out magnifying glass (may be a hidden toolbar icons)
2. This graph by default comes in displying Peak Units. I prefer to examine Work. To see the Work graph;
-Right click in the timephased area of the bottom graph and click on Work
-I also like to show the availability line in this graph.
-Right click in the timephased portion again
-Click on Bar Styles
-Check the Show Availability Line
Hope this helps!
J Black