×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Problems with how Project calculates Duration

Problems with how Project calculates Duration

Problems with how Project calculates Duration

(OP)
I would like Duration to automatically calculate based on Work and Resources.  Project seems to work fine, when using one resource, but using multiple resources, the Duration calculation appears to be off.  As an example, I will create a task for 10d (80hrs), and add two resources (one full-time and one part-time), at 75% each (9hrs/day combined).  I would assume the Duration would calculate to 8.88d(80hrs/9hrs) and an End Date of 4/20/06 (if started on 4/10/06), but it instead calculates to 9.92d.  Not only that, but the End Date is calculated to 4/28/06 (which is 15 business days long).  What am I missing?

RE: Problems with how Project calculates Duration

how are you entering the data and in what order?

your statement about "9hrs/day combined" does not jibe with "75% each," which should be more like 12hrs/day combined

In any case with a[1],b[0.125], I get 8.85 days for 80 hrs of work.

TTFN



RE: Problems with how Project calculates Duration

(OP)
I'll try to reword.  I have one full-time resource (8hrs/day).  That resource can only spend 75% of their time on the task (6hrs/day).  I have another resource, which is a part-time resource (4hrs/day).  That resource also can only spend 75% of their time on the task (3hrs/day).  The 6hrs + 3hrs is where I was getting the 9hrs (or (8+4)*.75%).  Hope that makes more sense.

As for the entering of data, I have tried multiple different orders.  I've tried work, resource 1, and then resource 2, and duration still does not calculate based on how I think it should.

Thanks

RE: Problems with how Project calculates Duration

You must enter both resources AT THE SAME TIME

TTFN



RE: Problems with how Project calculates Duration

(OP)
I tried it multiple different ways, and here are the results:
  1) Add Resource 1 @ 75%, and then add Resource 2 @ 75%.  Duration calculates at 9.83d.  The difference between the Start and End Dates is 13d.
  2) Add Resource 1 and Resource 2 @ 100%, then change Resource 1 % to 75%, and then change Resource 2 % to 75%.  Duration calculates at 10d.  The difference between the Start and End Dates is 14d.
  3) Add Resoucre 1, then add Resource 2, then change Resource 1 % to 75%, and then change Resource 2 % to 75%.  Duration calculates at 1017d.  The difference between the Start and End Dates is 14d.
  4) Add Resource 1 @ 113% (which is really what Resource 1 and Resource 2 are at 75%).  Duration calculates at 8.85d.  The difference between the Start and End Dates is 9d.  This is the one that calculates correctly.  I would think the first three would calculate the same way.

To setup a part-time resource, I'm using the calendar, setting them to work 4hrs/day (8am - 12pm).  Based on this, I'm assuming I can work this resource at 75%, which would be a total of 3hrs.

Thanks

RE: Problems with how Project calculates Duration

No, you need to enter all the correct values at the same time!

you type r1[0.75],r2[0.75] in ONE OPERATION.  DO NOT EDIT, DO NOT CHANGE.

TTFN



RE: Problems with how Project calculates Duration

(OP)
It calculates the same as option 3 above.  No difference.

RE: Problems with how Project calculates Duration

then you need to split the task

TTFN



Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

Low-Volume Rapid Injection Molding With 3D Printed Molds
Learn methods and guidelines for using stereolithography (SLA) 3D printed molds in the injection molding process to lower costs and lead time. Discover how this hybrid manufacturing process enables on-demand mold fabrication to quickly produce small batches of thermoplastic parts. Download Now
Design for Additive Manufacturing (DfAM)
Examine how the principles of DfAM upend many of the long-standing rules around manufacturability - allowing engineers and designers to place a part’s function at the center of their design considerations. Download Now
Taking Control of Engineering Documents
This ebook covers tips for creating and managing workflows, security best practices and protection of intellectual property, Cloud vs. on-premise software solutions, CAD file management, compliance, and more. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close