Problems with how Project calculates Duration
Problems with how Project calculates Duration
(OP)
I would like Duration to automatically calculate based on Work and Resources. Project seems to work fine, when using one resource, but using multiple resources, the Duration calculation appears to be off. As an example, I will create a task for 10d (80hrs), and add two resources (one full-time and one part-time), at 75% each (9hrs/day combined). I would assume the Duration would calculate to 8.88d(80hrs/9hrs) and an End Date of 4/20/06 (if started on 4/10/06), but it instead calculates to 9.92d. Not only that, but the End Date is calculated to 4/28/06 (which is 15 business days long). What am I missing?
RE: Problems with how Project calculates Duration
your statement about "9hrs/day combined" does not jibe with "75% each," which should be more like 12hrs/day combined
In any case with a[1],b[0.125], I get 8.85 days for 80 hrs of work.
TTFN
RE: Problems with how Project calculates Duration
As for the entering of data, I have tried multiple different orders. I've tried work, resource 1, and then resource 2, and duration still does not calculate based on how I think it should.
Thanks
RE: Problems with how Project calculates Duration
TTFN
RE: Problems with how Project calculates Duration
1) Add Resource 1 @ 75%, and then add Resource 2 @ 75%. Duration calculates at 9.83d. The difference between the Start and End Dates is 13d.
2) Add Resource 1 and Resource 2 @ 100%, then change Resource 1 % to 75%, and then change Resource 2 % to 75%. Duration calculates at 10d. The difference between the Start and End Dates is 14d.
3) Add Resoucre 1, then add Resource 2, then change Resource 1 % to 75%, and then change Resource 2 % to 75%. Duration calculates at 1017d. The difference between the Start and End Dates is 14d.
4) Add Resource 1 @ 113% (which is really what Resource 1 and Resource 2 are at 75%). Duration calculates at 8.85d. The difference between the Start and End Dates is 9d. This is the one that calculates correctly. I would think the first three would calculate the same way.
To setup a part-time resource, I'm using the calendar, setting them to work 4hrs/day (8am - 12pm). Based on this, I'm assuming I can work this resource at 75%, which would be a total of 3hrs.
Thanks
RE: Problems with how Project calculates Duration
you type r1[0.75],r2[0.75] in ONE OPERATION. DO NOT EDIT, DO NOT CHANGE.
TTFN
RE: Problems with how Project calculates Duration
RE: Problems with how Project calculates Duration
TTFN