×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Wrapping vs Coating for Underground Piping

Wrapping vs Coating for Underground Piping

Wrapping vs Coating for Underground Piping

(OP)
Hi Guys,

Anyone got something to share on the protection of the underground (UG) piping?

For our project, based on the specification, the UG piping (firewater line and oily water sewer line) needs to be coated and wrapped. We had a meeting this morning & somebody mentioned that it is either coated or wrapped.

Just to check, what is the common practice in oil & gas industry? Is it adequate to just coated without wrapping with tape?

If we need to wrap, is it normal to do it at site or at factory? Do we have machine pipe wrapping? or is it practical/economical to do it manually?

Thanks

norzul

RE: Wrapping vs Coating for Underground Piping

(OP)
The total firewater line (6") is about 4km. The oily water sewer line (4") about 2km.

After further investigation, now I realize that there are 2 methods of UG pipe protection
1) TAPE WRAPPING - manual vs machine
2) COATING like Yellow Jacket

Prior to above, still need to do surface preparation of the pipe:
1) Blasting
2) Primer - coating (1st coat & 2nd coat)

For such a relatively short pipe (2-4km), is it economic to have COATING? I was informed that for very long natural gas pipeline, normally it is COATED...

Thanks

norzul  

RE: Wrapping vs Coating for Underground Piping

There are a number of factors at play here including: criticality of the lines, leak tolerance, application of CP, life cycle costs, etc etc.  Shop coating will always give you a better quality coating but what then for the field joints?  Tape wrap can disbond and shield the pipe from CP leading to corrosion.  'Coating' could also include spray painting if you are confident about the CP system design and the monitoring procedures.  The principal point is that the coating will be the first line of defence against corrosion and that it is backed up by a CP system.

Steve Jones
Materials & Corrosion Engineer
http://www.pdo.co.om/pdo/

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close