Forward launching pre-cast girders
Forward launching pre-cast girders
(OP)
Can anybody help me with info about forward launching truss or nose for a span of 95' and a box girder of 72 tons? Any other ideas welcomed.
Details: RR bridge 8 spans, 5 girders per span, I would like to erect them from the top (deep canyon underneath).
Details: RR bridge 8 spans, 5 girders per span, I would like to erect them from the top (deep canyon underneath).
RE: Forward launching pre-cast girders
RE: Forward launching pre-cast girders
Theory and Design of Bridges
Petros P. Xanthakos
Wiley Interscience, New York 1994
in chapter 8 treats segmental construction (span per span as well) and has ample bibliography from where to expand study.