INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

MSPROJECT 2000 : Strange behaviour after merge

MSPROJECT 2000 : Strange behaviour after merge

MSPROJECT 2000 : Strange behaviour after merge

(OP)
With MS PROJECT 2000 ; A strange behaviour when a couple of projects are linked in a master project.

What exactly I did.

- I planned separately 3 projects : P1, P2, P3.
- I insserted the 3 projects in a central one : PMASTER.
- I defined a resource pool in PMASTER and allowed P1, P2 and P3 to share resources.
- The  efforts (Work) et Duration values unit is «day».

First result (seems to be correct).

- In a first check ; the merge worked but one task of P1 is marked «critical» in PMASTER and not in P1 plan.

Second result (Strange!).

- 24 hours after, I reopen the 4 files. Surprise ! Durations have been automatically recalculated and replaced by other numbers with decimal digits ???

- Also, anytime I open the PMASTER project, a second file (Project1) is created. The content of Project1 is very similar to the content of PMASTER ???

- A look to the «resource usage» table does also show me (for a week, 5 days planning) the values 1.14d    1.14d    1.14d    1.14d    1.14d instead of 1d 1d 1d 1d 1d ???

- The critical task is still «critical» in PMASTER and not in P1. I do not understand why ???

Thanks in advance for your help.

RE: MSPROJECT 2000 : Strange behaviour after merge

The subprojects may have been changed to decimal units because PMASTER uses decimal units - I remember seeing "how to convert fractional to decimal units" in my manual the other day, but now I can't find it.  Anyway, the master can cause these sorts of changes in the subs.

Project1 is created when you select the wrong option when opening the master resource pool (in your case PMASTER).  Choose one of the other opening options.

Check your resource calendar for allowable working time.  Also be sure you understand task types: fixed duration -vs- work -vs- units -vs- effort driven.  The wrong selection can give unxpected results.

P! cannot know the critical path of the overall project plan since it has no visibility of the overall plan.  only PMASTER can know the overall crit path.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close