Jul 30, 2005 #1 bmsg Electrical Joined Oct 27, 2003 Messages 45 Location IN Is it possible to generate a planned progress vs. actual progress curve from MS Project? If yes, how?
Is it possible to generate a planned progress vs. actual progress curve from MS Project? If yes, how?
Aug 2, 2005 #2 WillRussell Mechanical Joined Nov 18, 2003 Messages 31 Location GB Copy the data "work" and "actual work" in the right hand pane of the task usage view into MSExcel and create your graph there. This is the only method I've found to be of any use. Will Upvote 0 Downvote
Copy the data "work" and "actual work" in the right hand pane of the task usage view into MSExcel and create your graph there. This is the only method I've found to be of any use. Will