-
1
- #1
PEinc
Geotechnical
- Dec 2, 2002
- 4,088
I was taught to size a pile driving hammer so that the pile reaches the desired capacity at approximately 10 to 12 blows per inch. (I know that some agencies require all piles to be driven to refusal at 20 blows per inch). Lately, it seems that people are driving piles to capacity with larger pile hammers and much fewer blows per inch, such as 1 to 4 blows per inch.
On a recent project I was involved with, GRL ran a WEAP analysis that told the contractor to drive the 75' long , 100 kip ultimate capacity, HP12x53 piles 70 feet through soft organic silts, through medium sand, into denser sand at only 10.2 blows per foot with an APE D19-42 diesel hammer having 41.8 ft-kips maximum rated energy. I reviewed the WEAP printout and everything looked OK. However, it seems to me that 10 blows per foot is not enough resistance to confidently determine the pile's ultimate capacity. I personally would have called for a smaller pile hammer or turned down the fuel setting in order to raise the required blows per inch. I like to see a pile "take up" as the blow count increases.
What amount of hammer blows are you looking at when sizing a hammer and determining ultimate pile capacity? Comments?
On a recent project I was involved with, GRL ran a WEAP analysis that told the contractor to drive the 75' long , 100 kip ultimate capacity, HP12x53 piles 70 feet through soft organic silts, through medium sand, into denser sand at only 10.2 blows per foot with an APE D19-42 diesel hammer having 41.8 ft-kips maximum rated energy. I reviewed the WEAP printout and everything looked OK. However, it seems to me that 10 blows per foot is not enough resistance to confidently determine the pile's ultimate capacity. I personally would have called for a smaller pile hammer or turned down the fuel setting in order to raise the required blows per inch. I like to see a pile "take up" as the blow count increases.
What amount of hammer blows are you looking at when sizing a hammer and determining ultimate pile capacity? Comments?