sahelrahman
Electrical
- Dec 3, 2010
- 25
I am currently working on coordination study of a project. The curves of few breakers are overlapped. So it is tough to say which one will trip first. But what I understood is that, since the breaker trip units used has the characteristic of Zone selective Interlocking (ZSI) , the breakers communicate with each other and it makes sure that the downstream breaker trips before the upstream breakers. Am I right?