GoldDredger
Civil/Environmental
- Jan 16, 2008
- 172
I was recently involved with a project where we (site engineers) were co-consultants with the architects to the developer. Unfortunately, we suffered from considerable scope creep due to this arrangement. This project was a 40 acre mall complex, with numerous buildings and about 3 separate architects.
One large problem was the constant modification of building footprints, which seemed to change on a regular basis. (One building may have changed 10 times). Each time we had to re-insert the footprint, modify the drawings, and issue a new addendum.
Another problem was that the MEP design lagged behind the site civil approval. During the civil design and approvals, we could only provide a ‘best guess’ of sewer, domestic and fire connections into the buildings. These ended up changing, both in size, invert and location, which in turn required modifications to the utility drawings.
In some cases, the changes seemed to have a cascading affect. For example moving an architectural column would place it too close to a curb inlet, or handicap ramp, which would require other changes to the civil drawings. Or moving a door required moving a dumpster, which in turn affected the curb and elevations down the way. My favorite was adding a new recessed loading dock, requiring a storm drain line to be designed where non was previously proposed.
The developer (who were every bit as ‘slippery’ as one might expect), would constantly fight us for every extra dime we might seek for these changes or coordination. Although we were entitled to seek these extras, doing so unfortunately seemed to generate animosity. (They are no longer our clients, and as rumor has it, have used up half the engineers in town)
Anyway, for brevities sake I haven’t included all the details. For example I was hired and began project managing this well after the poorly defined contract was established. The contractors made numerous mistakes. There was just a litany of problems.
My question though, is have any of you encountered this architect-engineer coordination problem? How have you handled or anticipated this in your original contract?
Also, as I have learned, whenever there is a problem, even if it is not your fault, will cost you time and effort to prove it’s not your fault, or at least in helping to find a resolution. I (will)try to preempt problems by identifying them early with architects.
Do any of you have a checklist you use at the beginning of a project for the architect? (In fairness to architects, many changes may be developer or tenant driven, and not entirely within their control)