SparkyLarks
Electrical
- Jul 14, 2005
- 43
I work for a company that makes a small number of machines, and does work CE Marking third party machines.
EN60204-1 says that you may need to perform Insulation Resistance tests but gives no guidance on when you may need to perform them. I'm trying to develop a few guidelines on when we should perform insulation resistance tests. (Customers won't pay us if we price in insulation resistance of every Transformer, motor, and cable)
We sometimes are asked to CE new machine imported from the US, or Check compliance of old machines. Legally the requirement for insulation testing is determined by the risk assessment. But I can't say to customers I need to test all motors, even 50W motors.
One suggestions was if you can't lift it , then Test it
I was thinking of proposing
1) If a cable is longer than 20m then Test it
2) If a cable carries greater thatn 63 A then Test it
3) Motors >25kW then Test it
4) Transformers > 10kVA the Test it
Does that sound reasonable?
We would of course be recommending that the customer should test motors and transformers as part of routine maintenance.
We will bench test motors and transformers for machines we build ourselves. Cables we install on site will also be IR tested( Part of the legal tests required for installations.)
EN60204-1 says that you may need to perform Insulation Resistance tests but gives no guidance on when you may need to perform them. I'm trying to develop a few guidelines on when we should perform insulation resistance tests. (Customers won't pay us if we price in insulation resistance of every Transformer, motor, and cable)
We sometimes are asked to CE new machine imported from the US, or Check compliance of old machines. Legally the requirement for insulation testing is determined by the risk assessment. But I can't say to customers I need to test all motors, even 50W motors.
One suggestions was if you can't lift it , then Test it
I was thinking of proposing
1) If a cable is longer than 20m then Test it
2) If a cable carries greater thatn 63 A then Test it
3) Motors >25kW then Test it
4) Transformers > 10kVA the Test it
Does that sound reasonable?
We would of course be recommending that the customer should test motors and transformers as part of routine maintenance.
We will bench test motors and transformers for machines we build ourselves. Cables we install on site will also be IR tested( Part of the legal tests required for installations.)