Jrattray
Electrical
- Nov 25, 2008
- 1
As part of scheduling an upgrade of a radial spur to a net worked solution I am trying to get a feel for what is current best practice. The first step will be a presentation to the regulator on what other countries / states do.
I know some jurisdictions go N-1 at 10, 15 or 25 MVA, some on least cost between lost energy and the cost of the upgrade; in the latter using a value for lost energy at about $25,000 a MWh.
What would be appreciated is any thoughts on what is the process outside of Australia.
Thanks in advance for your time
I know some jurisdictions go N-1 at 10, 15 or 25 MVA, some on least cost between lost energy and the cost of the upgrade; in the latter using a value for lost energy at about $25,000 a MWh.
What would be appreciated is any thoughts on what is the process outside of Australia.
Thanks in advance for your time