what is the minimun distance into the concrete for a brige pile (the pile a HP section)?

Status
Not open for further replies.

cris300

Structural
Jun 28, 2012
20
Capture_u6g2wt.png



and what do you think about the reinforcement propose?
stirrups and vertical rebars

thanks in avance
 
Replies continue below

Recommended for you

Does the agency you're working for have any requirements? As SRE said, 6" minimum is common but agencies have exceptions to the rule of thumb. For example, with NYSDOT the embedment can be anywhere fro 6" to 2'. A few thoughts...do you need to slope the abutment stem? That's a pain the @$$ to form. Flying wingwalls are typically tied to the abutment stem and not the footing.
 