Nov 8, 2006 #1 redandysafc Mechanical Joined Dec 18, 2005 Messages 60 Location GB If a welder gets a repair using smaw does his two coverage butts ahve to be the same process.
Nov 8, 2006 #2 metengr Materials Joined Oct 2, 2003 Messages 15,478 Location US What????????????????? Please restate your question with more information. Upvote 0 Downvote
Nov 9, 2006 Thread starter #3 redandysafc Mechanical Joined Dec 18, 2005 Messages 60 Location GB When a welder gets a repair on say a 10% line do the 2 repairs that cover the repair have to be the same process. We are working to asme Upvote 0 Downvote
When a welder gets a repair on say a 10% line do the 2 repairs that cover the repair have to be the same process. We are working to asme
Nov 9, 2006 #4 metengr Materials Joined Oct 2, 2003 Messages 15,478 Location US Question; When a welder performs a weld repair on a pressure retaining item, is it required that subsequent weld repairs in or adjacent to the original repair location be performed using the same welding process? Reply; No. Upvote 0 Downvote
Question; When a welder performs a weld repair on a pressure retaining item, is it required that subsequent weld repairs in or adjacent to the original repair location be performed using the same welding process? Reply; No.