anchorengineer
Structural
- May 26, 2009
- 88
I've seen a lot of topics regarding cold joints in concrete slabs/beams/walls that deal mostly with structural capacities but I haven't seen a solid answer to waterproofing the joint.
I've been asked by a contractor to review a slab that was supposed to be poured monolithically but the last concrete truck was late and rejected. The slab is for a vessel at a WWTP. The slab was designed to be 1 ft thick and to have a 1ft wide frost/edge beam around the perimeter. Instead of forming the frost beam he sloped the inside of it creating a large haunch and instead of a 12" slab his slab is more like 17" thick. Unfortunately the first pour was not level so the concrete rose above the top rebar mat on one side and the other side was below the bottom mat. They took pictures after the first pour and the concrete was plenty roughened.
My main concern is since this is a WWTP it will be exposed to some nasty stuff. I'm concerned more for the performance of the slab over time than anything. I considered using a waterproofing product along the sides to hold out the moisture but I'm not sure if it's lngevity.
Any thoughts?
Clarke Engineering Services, PC
Jobsite Engineering and Consulting
I've been asked by a contractor to review a slab that was supposed to be poured monolithically but the last concrete truck was late and rejected. The slab is for a vessel at a WWTP. The slab was designed to be 1 ft thick and to have a 1ft wide frost/edge beam around the perimeter. Instead of forming the frost beam he sloped the inside of it creating a large haunch and instead of a 12" slab his slab is more like 17" thick. Unfortunately the first pour was not level so the concrete rose above the top rebar mat on one side and the other side was below the bottom mat. They took pictures after the first pour and the concrete was plenty roughened.
My main concern is since this is a WWTP it will be exposed to some nasty stuff. I'm concerned more for the performance of the slab over time than anything. I considered using a waterproofing product along the sides to hold out the moisture but I'm not sure if it's lngevity.
Any thoughts?
Clarke Engineering Services, PC
Jobsite Engineering and Consulting