Ingenuity
Structural
- May 17, 2001
- 2,374
I was at a site meeting recently and the waterproofing consultant was discussing a proposed detail to the GC and architect where a new concrete beams interface with an existing roof slab. See sketch below.
The structural drawings detail a roughened interface across the joint with vertical post-installed dowels, at varying spacing (#5@6" and #5@12", so pretty decent size and spacing), so clearly the SER was looking for some composite/bonded action.
The waterproofing is detailed to pass through the interface. I questioned the waterproofing consultant (one of the larger multi-office consultants) and he said it was vetted through the structural engineer and it is acceptable.
The waterproofing is a cold, liquid-applied, roller-application product.
I would have lapped the WP up the vertical sides of the new beam and NOT passed it through the interface.
Anyone used or seen such a detail across an interface?
The structural drawings detail a roughened interface across the joint with vertical post-installed dowels, at varying spacing (#5@6" and #5@12", so pretty decent size and spacing), so clearly the SER was looking for some composite/bonded action.
The waterproofing is detailed to pass through the interface. I questioned the waterproofing consultant (one of the larger multi-office consultants) and he said it was vetted through the structural engineer and it is acceptable.
The waterproofing is a cold, liquid-applied, roller-application product.
I would have lapped the WP up the vertical sides of the new beam and NOT passed it through the interface.
Anyone used or seen such a detail across an interface?
