mzaitz
Structural
- Sep 15, 2005
- 30
All
We have an aeration basin that is approximately 128 ft by 130 ft in plan with a 61 ft by 40 ft corner cut out. The contractor has submitted an RFI to place this 2 ft thick mat in 1 day. It is approximately 1130 cy of concrete. The mat is reinforced with 2 layers of #6 at 6" o.c. Currently we show construction joints about 30 feet on center. I have seen larger pours than this for a mat but never for a water retaining structure. I am very concerned about the structure cracking (then leaking) due to shrinkage. Has anyone done a mat this size in one day for water retaining structures? Any advice on it?
Thanks,
Mike
We have an aeration basin that is approximately 128 ft by 130 ft in plan with a 61 ft by 40 ft corner cut out. The contractor has submitted an RFI to place this 2 ft thick mat in 1 day. It is approximately 1130 cy of concrete. The mat is reinforced with 2 layers of #6 at 6" o.c. Currently we show construction joints about 30 feet on center. I have seen larger pours than this for a mat but never for a water retaining structure. I am very concerned about the structure cracking (then leaking) due to shrinkage. Has anyone done a mat this size in one day for water retaining structures? Any advice on it?
Thanks,
Mike