marinaman
Structural
- Mar 28, 2009
- 195
I've been thinking about a column splice that I need to design. I have a W10x77 column running from the foundation, thru the second floor, to the roof of my building. At the roof elevation, due to geometry of the structure above, I'm going to need to transition my column from a W10x77 to an HSS 10 pipe column.
I've looked hard at the AISC steel manual and have not found a column splice that accomodates what I'm describing.
The loads are small, compared to the size of the columns. I've got around 80 kips thru the 10" pipe being sent thru to the W10x77.
My question is about the splice.
AISC recommends 1 1/2" thick butt plates for a W8 to W10 splice....and a 2" butt plate on W10 to W12's.
What I was thinking of doing is placing a 1 1/2" cap plate on my W10x77, then, a 1 1/2" baseplate on my HSS 10 columns, and then, setting the HSS 10 on top of my W10 and simply bolting the HSS 10 baseplate to the W10 cap plate via (4) 1" diameter A325 bolts. This splice would occurr at the roof framing diaphragm elevation and would therefor be laterally stable. I do not need moment capacity thru the splice.
Seems pretty simple, but wanted to be sure I'm not missing something here.
Any opinions on this splice? See a better way to do it?
I've looked hard at the AISC steel manual and have not found a column splice that accomodates what I'm describing.
The loads are small, compared to the size of the columns. I've got around 80 kips thru the 10" pipe being sent thru to the W10x77.
My question is about the splice.
AISC recommends 1 1/2" thick butt plates for a W8 to W10 splice....and a 2" butt plate on W10 to W12's.
What I was thinking of doing is placing a 1 1/2" cap plate on my W10x77, then, a 1 1/2" baseplate on my HSS 10 columns, and then, setting the HSS 10 on top of my W10 and simply bolting the HSS 10 baseplate to the W10 cap plate via (4) 1" diameter A325 bolts. This splice would occurr at the roof framing diaphragm elevation and would therefor be laterally stable. I do not need moment capacity thru the splice.
Seems pretty simple, but wanted to be sure I'm not missing something here.
Any opinions on this splice? See a better way to do it?