Arevaengineer
Electrical
- Feb 3, 2004
- 46
We have 132kV GIS switchgear with outgoing cables connnected. The cable needs to be tested at HV AC at 75kV. The voltage transformer is a fixed type above the cable box. Disconnecting mean are provided inside the cable box, but degassing would be required to remove that link.
Should the GIS be disconnected from the cable?
Should the GIS be disconnected from the cable?