JKJohn
Structural
- Oct 27, 2008
- 49
Three separate foundation systems. All are in the same job site and all are delegate design. There are Underpinning, Auger Cast Piles, and concrete driven piles.
We initially had the driven piles go in first, then underpinning, then auger piles.
We had delays and at this point we are going to have to do all three almost at the same time.
Soil on site is soft.
We asked the auger pile concrete when we could drive the concrete pile next to their piles, they answered after one day.
I am not convinced.
I would like to know your thoughts and does anyone have any reference?
Thanks in advance!!
We initially had the driven piles go in first, then underpinning, then auger piles.
We had delays and at this point we are going to have to do all three almost at the same time.
Soil on site is soft.
We asked the auger pile concrete when we could drive the concrete pile next to their piles, they answered after one day.
I am not convinced.
I would like to know your thoughts and does anyone have any reference?
Thanks in advance!!