dik
Structural
- Apr 13, 2001
- 26,063
I've got a small project where a 70' utility pole is embedded 10% of the length in 'Shield' rock. I'm looking at using a program I wrote using the Bowling method with a high K value. I suspect anything that happens will occur within the first few feet due to the rock stiffness.
Any comments or suggestions why Bowling is inappropriate, or, is there a better approach?
Dik
Any comments or suggestions why Bowling is inappropriate, or, is there a better approach?
Dik