steelfab37
Structural
We have a small problem with a project that we're working on. There is a dimensional discrepancy between the architectural dimensions for a drive thru canopy that we are fabricating (I work for the fabricator) and what the structural EOR has placed on the contract documents. Apparantly the EOR is going to be responsible for the cost of the change directly. My issue is that this change will not be part of the contract and will be paid directly from the Engineer, therefore cutting out contractual obligation of payment.
My question is, is this a normal practice that we have just not seen yet, or should we try to force this into the contract (standard AIA contract)? We've produced some 400 odd structures from $10,000 to $1.2 mil. and have never had this situation come up, making us very leery in agreeing to the terms. I will have some form of small contract written out for this with the EOR, but the seperation of this change from the actual contract sounds fishy.
I'd like to hear your thoughts, I have a great respect for all of the members on this forum and have learned quite a lot from the questions and answers over the years. Also, apologies if this is an inappropiate topic, I'll remove it if so. I just figured that if this practice has been done before, someone on this board will know of it and be able to give us pointers in how to handle the situation.
Thanks.
In case anyone is wondering, the drawings were submitted with questions on these particular dimensions and were verified in writing on the dimenions lines by the EOR, Arch, and G.C. The beams, columns, canopy segments, and all misc parts were fabricated according to the verified dimensions before the Arch decided that they needed to be changed, thus the change order...otherwise this would have been a moot point for us.
My question is, is this a normal practice that we have just not seen yet, or should we try to force this into the contract (standard AIA contract)? We've produced some 400 odd structures from $10,000 to $1.2 mil. and have never had this situation come up, making us very leery in agreeing to the terms. I will have some form of small contract written out for this with the EOR, but the seperation of this change from the actual contract sounds fishy.
I'd like to hear your thoughts, I have a great respect for all of the members on this forum and have learned quite a lot from the questions and answers over the years. Also, apologies if this is an inappropiate topic, I'll remove it if so. I just figured that if this practice has been done before, someone on this board will know of it and be able to give us pointers in how to handle the situation.
Thanks.
In case anyone is wondering, the drawings were submitted with questions on these particular dimensions and were verified in writing on the dimenions lines by the EOR, Arch, and G.C. The beams, columns, canopy segments, and all misc parts were fabricated according to the verified dimensions before the Arch decided that they needed to be changed, thus the change order...otherwise this would have been a moot point for us.