PEDARRIN2
Mechanical
- Oct 1, 2003
- 1,287
I am designing the piping and equipment for a fire suppression system which includes an underground concrete storage tank. The tank will be located below an expansion of the existing building. Some of the walls of the tank will also serve as the foundation of a part of the building.
The way I read and interpret NFPA 22 is that the tank walls must be poured concrete construction.
The architect wants to use a block wall construction.
I need to know if I should bring this up.
Thanks
The way I read and interpret NFPA 22 is that the tank walls must be poured concrete construction.
The architect wants to use a block wall construction.
I need to know if I should bring this up.
Thanks