This is carefully written and very restrained report; it refrains from asking some important questions, though I have no doubt these questions will be asked and answered in subsequent reports, in the press and by politicians.
This is not an area of expertise for me but logic suggests some seemingly obvious questions.
For example, many of the investigations post-mortem would seem could reasonablly be expected to form part of the onsite routines, especially when preparing to receive fuels.
The estimation of filling time or end point based on flow rates and tank capacity is such a simple routine it could be automated in the control systems/
Question:
Is this calculation made manually by the operators and/or within the system? Is it also performed at the supply end of the pipeline relative to the amount to be delivered?
Question:
By how much did the planned 8300m3 delivery overshoot?
Are there any routines at the supply end that can be applied to prevent oversupply?
Could they not determine this because more than one site was being supplied?
Surely they would need access to flow instrumention to monitor what was being delivered and where?
This calculation is eminently feasible given that it has been done in the post mortem.
Question:
The investigators have been able to test many elements of the instrumentation. Are these tests that would be routinely performed in preparation for receiving fuels?
If not, are they routine at any time?
When they were last performed?
Question:
Is it routine to manually dip the tanks? if so when? In preparation for eceiving fuels? When doing a stock check as at midnight?
On the face of it there ought to have been a reasonable probability that three or four or more diferent mechanisms existed to detect when the tank should have been full both through the instrumentation, on site and off, and at the supply end, and through observation and calculation.
We have the ATG, an "ultimate" high level switch, tank dipping, remote monitoring, instrument systems tests, flow calculations that can be perfomed, manually, atomatically and some which can be performed at supply end of the pipeline.
The use of the temperature readings is another missed indication and it is not an obscure clue, operators should be familiar enough to recognise the importance of other instruments as diagnostics when checking the potential failure of a key instrument.
There is also CCTV footage but apparently no one was watching at the time i.e any time from 05:20 till 06:01.
Question:
Should there be level indicators in the bunds? are there gas detectors in the immediate vicinity of the tanks? would this be usual or not?
Question:
Would it not be normal for a periodic review of all site safety routines, for routine testing of the instrumentation, a review of the procedures and, perhaps most importantly, to test for compliance?
Question:
What is the probability that all systems failed at the same time?
Is it more likely that the different parts of the system failed at different times?
Is it possible that some failures were not found e.g. the "ultimate" high level switch was never found to have failed bacuse the ATG normally never let the level reach this switch; the first indication it has failed is when the ATG fails?
So, is there a log of instrument testing and any reported failures?
Obvioulsy these are questions in response to the little I know from the reports and the even less that I know about what should go on.
Am I unrealsitic? or is this hindsight?
JMW