majesus
Electrical
- Aug 16, 2007
- 262
I am trying to find a unit cost for decommissioning and removing of O/H transmission lines. 2016 PG&E Final Generator Interconnection Unit Cost Guide has the following:
Double Circuit (per mile, $x1000)
69kV = 420
115kV = 420
230kV = 650
Those published values seems high for removal of lines and towers on typical, flat terrain. I was curious if anyone has additional cost estimates for removal of O/H transmission lines that can collaborate.
Double Circuit (per mile, $x1000)
69kV = 420
115kV = 420
230kV = 650
Those published values seems high for removal of lines and towers on typical, flat terrain. I was curious if anyone has additional cost estimates for removal of O/H transmission lines that can collaborate.