Does anybody out there know if it is possible to show two lines on the resource graph. E.g the resource graph currently shows a line on the peak units view which represents a straight line for max availability of resource, I am trying to show another line for budgted availability of resource over the next twelve months, however unsure as to whether two lines can be represented.
Many thanks,
Clive Green (0115 992 2876).
Many thanks,
Clive Green (0115 992 2876).