Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

tunnel lining penetration

Status
Not open for further replies.

par060

Structural
Feb 28, 2001
146
A project we are working on requires a penetration through a existing concrete tunnel lining. The tunnel is in rock we are drilling a vertical shaft to the required elevation. the problem is that there is approx 20' of head above the tunnel. How can we limit the amount of water flowing into the tunnel?
 
Replies continue below

Recommended for you

can you plug the tunnel in the vicinity of the penetration and then construct the shaft? Once you have constructed it, remove the temporary plugs.
 
No the tunnel's primary use is for a commuter train...the ID is 16'
 
it might be possible to grout in a ring around the proposed shaft area and reduce infiltration. your geotech could answer that question
 
Call a few well drillers for advise. All else fails, Call Tri-State Well drillers in Minnesota. I have used them for this type of construction in the past. Sorry i don't live there any more and do not have a number for you. They should be in the Minneapolis phone book.

Richard A. Cornelius, P.E.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor