WE HAVE A 15 MVA SUBSTATION , THE PRIMARY VOLTAGE TO THE SUBSTATION IS 115K THE SECONDARY IS
4160. WE HAVE A EXISTING M.C.C. WHICH IS FEED FROM THE SUBSTATION THOUGH A 2000A O.C.B.,
WE RECEIVE THE 2000A 4160V INTO OUR M.C.C. WE THEN DISTRIBUTE THE 4160 TO SEVERAL MED.
VOLTAGE MOTORS AND TWO 4160/480V TRANSFORMERS WHICH FEED OUR LOW VOLTAGE M.C.C.S.
THIS SYSTEM HAS A GROUND GRID WHICH GOES THOUGH THE WHOLE FACILITY AND IS TIED BACK INTO
THE SUBSTATIONS GROUND SYSTEM . WE ARE ADDING ANOTHER 1200A O.C.B.IN THE SUBSTATION.
WHICH WILL FEED THE 3000 KVA TRANSFORMER. MY QUESTION WAS SHOULD I BOND XO TO THE
EUIPMENT GROUND OF THE TRANSFORMER WHICH WILL BE GROUND TO THE THE MAIN GRID.
THIS 3000KVA TRANSFORMER IS FEEDING A MCC THE XO WILL BE ATTACHED TO THE GROUND
OF THE MCC AND IT WILL BE BOND TO THE MAIN GRID OF THE FACILITY . BUT DOES IT MATTER IF
I BOND IT TO THE EQUIPMENT GROUND AT THE TRANSFORMER.