I inherited an MS Project 2003 .mpp that needs a total overhaul. I have never done such extensive modifications.
Current:
5 days / week
M - F, 8 hrs /day (0800 - 1200, 1300 - 1700)
Single Shift
Non-Resourced
Needed Conversion:
6 days / week
M - F, 10 hrs / day (0700 - 1200, 1230 - 1730) & Sat, 8 hrs / day (0700 - 1200, 1230 - 1530)
Double Shift on part of the schedule
Fully Resourced
The effort was entered in as days for completion. So, the conversion needs to not touch the duration. It is understood that the Single Shift converted to the Double Shift should be one-half (or so, 8 hr day wrenches this) of the effort.
Man-hours and equipment-hours are to be extracted from this schedule.
Calendar setup and definition of working times as well as other details would be greatly appreciated.
Thank you all in advance.
Current:
5 days / week
M - F, 8 hrs /day (0800 - 1200, 1300 - 1700)
Single Shift
Non-Resourced
Needed Conversion:
6 days / week
M - F, 10 hrs / day (0700 - 1200, 1230 - 1730) & Sat, 8 hrs / day (0700 - 1200, 1230 - 1530)
Double Shift on part of the schedule
Fully Resourced
The effort was entered in as days for completion. So, the conversion needs to not touch the duration. It is understood that the Single Shift converted to the Double Shift should be one-half (or so, 8 hr day wrenches this) of the effort.
Man-hours and equipment-hours are to be extracted from this schedule.
Calendar setup and definition of working times as well as other details would be greatly appreciated.
Thank you all in advance.