- May 24, 2006
- 1
I just updated several sections of a baselined MS Project 2003 Plan. I had already situated a cost column (with $ totals). After adjusting the sections, the individual (low level) items do not roll up the total(s) correctly. The overall high level calculation is way overstated (almost double). I cannot seem to correct the problem or have Project invoke a recalculation. I have tried a number of things, to no avail. The official MS Project 2003 guide does not provide any insight that I can find. What am I missing? How do I overcome this? Any assistance would be great.