payaam2000
Mechanical
- Nov 14, 2011
- 44
Dear All
Kindly is requested to help me in judgment.
We are the client of a Gas offshore platform construction project. We have employed two contractor for this project:
One is dedicated for jacket/platform , the other one is for Drilling activities.
At the first of project Jacket/topside contractor has informed the drilling contractor that TDAD(Temporary Drilling Access Deck) elevation is +12.00 and drilling contractor has confirmed this elevation at the first of project.
As a matter of fact if drilling executed at elevation +12.00, then Xmas Tree would had clashes with topside piping , therefore we requested from jacket/topside contractor to shift the TDAD elevation from +12.00 to +10.00 and now everything is ok.
Now two contractor has conflict with each other and they say the other side is responsible for this rework/cost impact.
Topside contractor says that drilling contractor has confirmed elevation +12.00 and drilling contractor says that why Jacket/topside contractor did not request for Xmas tree specifications/Dwgs?
Now would you please guide me who is responsible for this conflict? Drilling contractor or Jacket/Topside contractor.
Looking forward for your reply
Best Regards
Kindly is requested to help me in judgment.
We are the client of a Gas offshore platform construction project. We have employed two contractor for this project:
One is dedicated for jacket/platform , the other one is for Drilling activities.
At the first of project Jacket/topside contractor has informed the drilling contractor that TDAD(Temporary Drilling Access Deck) elevation is +12.00 and drilling contractor has confirmed this elevation at the first of project.
As a matter of fact if drilling executed at elevation +12.00, then Xmas Tree would had clashes with topside piping , therefore we requested from jacket/topside contractor to shift the TDAD elevation from +12.00 to +10.00 and now everything is ok.
Now two contractor has conflict with each other and they say the other side is responsible for this rework/cost impact.
Topside contractor says that drilling contractor has confirmed elevation +12.00 and drilling contractor says that why Jacket/topside contractor did not request for Xmas tree specifications/Dwgs?
Now would you please guide me who is responsible for this conflict? Drilling contractor or Jacket/Topside contractor.
Looking forward for your reply
Best Regards