Many thanks for your of your comments, as per my study,
According to Babcock & Wilcox, the time between completion of welding and PWHT should be limited to 14 days maximum to minimize the risk of SCC:
Gold M, Hainsworth J, Tanzosh J M, ‘Service experience with design and manufacturing approaches with T/P91 materials’, Proc. EPRI Conf. ‘9Cr Materials Fabrication and Joining Technologies’, 10-11 July 2001, Myrtle Beach, South Carolina, USA
According to Vallourec & Mannesmann, the time between completion of welding and PWHT should be limited to 7 days maximum: Vallourec & Mannesmann Tubes, ‘The T91/P91 Book’, 1999
More recently, I have heard some people refer to a limit of 3 days or so, but I’ve not seen this in any document.
But these all I did not study in any quality procedures or in any standard/Code.