Double timber piles are used to support the guy wires of about 30m towers about 25 years ago.
The ground (riverbed) is about 2m of clayey silt underlain by clean sand materials to a depth of 30m. The depth of anchorpiles are not known. Field inspection shows that the anchor piles are inclined 10-20 degrees towards the tower.
For geotechnical performance monitoring of the anchor piles what approaches one should take.
Appreciate your feedback in advance.
The ground (riverbed) is about 2m of clayey silt underlain by clean sand materials to a depth of 30m. The depth of anchorpiles are not known. Field inspection shows that the anchor piles are inclined 10-20 degrees towards the tower.
For geotechnical performance monitoring of the anchor piles what approaches one should take.
Appreciate your feedback in advance.