05dtaylor
Civil/Environmental
- Feb 10, 2011
- 18
Background:
6'x 12' ID Concrete Tank with 5" Walls. I'm working with the bottom half of this tank. The height of this piece is 4'-3" Tall. It has 5" thick walls and a 7" thick base slab. It's monolithic.
This piece will be filled with a large amount of concrete to form some channels for a sanitary system. Estimated weight of the tank section is ~16,000 lbs and estimated weight of the concrete to be poured inside this section is 28,000 lbs. Due to the channel design, the lifting points will be located in the top face of the poured insert. Long "dog bones" will be used as lifting inserts. One placed at each corner located 12" away from both walls.
What i'm trying to figure out is how to attach the inner concrete to the tank so as to properly be able to lift this entire piece at once.
My boss wants to use Dayton threaded rebar splices as connections between the interfaces. According to dayton, a #4 female end splice has a minimum depth of 4" which means it would be able to be placed in the walls. a #6 female end splice has a minimum depth of 6" which means #6, #5, or #4 can be placed in the base slab.
I'm trying to figure out the shear capacity of the #4 connection.
Any help? or ideas?
Thank you
6'x 12' ID Concrete Tank with 5" Walls. I'm working with the bottom half of this tank. The height of this piece is 4'-3" Tall. It has 5" thick walls and a 7" thick base slab. It's monolithic.
This piece will be filled with a large amount of concrete to form some channels for a sanitary system. Estimated weight of the tank section is ~16,000 lbs and estimated weight of the concrete to be poured inside this section is 28,000 lbs. Due to the channel design, the lifting points will be located in the top face of the poured insert. Long "dog bones" will be used as lifting inserts. One placed at each corner located 12" away from both walls.
What i'm trying to figure out is how to attach the inner concrete to the tank so as to properly be able to lift this entire piece at once.
My boss wants to use Dayton threaded rebar splices as connections between the interfaces. According to dayton, a #4 female end splice has a minimum depth of 4" which means it would be able to be placed in the walls. a #6 female end splice has a minimum depth of 6" which means #6, #5, or #4 can be placed in the base slab.
I'm trying to figure out the shear capacity of the #4 connection.
Any help? or ideas?
Thank you