struengineer
Civil/Environmental
- Sep 29, 2005
- 33
I need to back fill a 50’x50’x12’ (deep) pit and build a pre-engineering building. The max load from each column (Total of 8) is 50 kip. I specify the select structure fill as backfill material. Backfill are required to be compacted (95%)every 8”. However, I am still afraid that this thick backfill will cause exessive settlement. I do not have a lot of this kind of experience. Is any engineer here can give me any suggestion on how to prevent the settlement in this situation? Thank you very much.