You could also ask "How many test borings?" My standard answer is "At least one". Then, when you are done, you will know how many, maybe. For triaxials, I'd say, as Geopaver, but I'd add, "none to rarely" for most jobs. They are expensive and, with competition, costs sometimes over ride wishes.