DirtDr
Geotechnical
- Jun 28, 2002
- 9
Description:
A contractor has proposed a value engineering change that will require driving H-piles that will be in tension. The load will be about 100 to 150 kips per pile. It will be driven through a 30-ft layer of slightly overconsolidated, non-plastic silt into an underlying layer of heavily overconsolidated clay. This clay has an OCR of between 10 to 20 (although some of the deeper samples had OCR about 7 based on DMT only), an undrained shear strength (based on back calculation of pile load tests, UU-triaxial, and PMT)of 8-kips/sq ft. Based on CIUC triaxial tests the effective phi-angle is 17 degrees with 700 lbs/sq ft cohesion. If the changed design is approved there will be at least one pull out test to failure.
Question:
The contractor is of the opinion that the undrained anaylsis is the critical case. We used effective stresses, ignored the cohesion since it would be disturbed by the pile driving and estimated pile lengths that were about double what the contractor estimated. It is doubtful if a pile as long as we estimated could even be driven that deep economically. At this point we have no CD triaxal tests.
Which soil parameters should be used? What other issues are involved in driving piles into OC clay?
A contractor has proposed a value engineering change that will require driving H-piles that will be in tension. The load will be about 100 to 150 kips per pile. It will be driven through a 30-ft layer of slightly overconsolidated, non-plastic silt into an underlying layer of heavily overconsolidated clay. This clay has an OCR of between 10 to 20 (although some of the deeper samples had OCR about 7 based on DMT only), an undrained shear strength (based on back calculation of pile load tests, UU-triaxial, and PMT)of 8-kips/sq ft. Based on CIUC triaxial tests the effective phi-angle is 17 degrees with 700 lbs/sq ft cohesion. If the changed design is approved there will be at least one pull out test to failure.
Question:
The contractor is of the opinion that the undrained anaylsis is the critical case. We used effective stresses, ignored the cohesion since it would be disturbed by the pile driving and estimated pile lengths that were about double what the contractor estimated. It is doubtful if a pile as long as we estimated could even be driven that deep economically. At this point we have no CD triaxal tests.
Which soil parameters should be used? What other issues are involved in driving piles into OC clay?