Looking to design a temporary bridge to span a 15 ft. hole. Have a 1" steel plate 4' x 8' and some hp 10x 42 steel piles. If I use 3 piles per plate do I need to put some cross members in it or will the plate/pile system carry a point load of 12500 lbs.