Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Superceding Drawings

Status
Not open for further replies.

REDesigner09

Aerospace
Nov 19, 2010
227
Hi Everyone,

I have casting & machine drawing that was created some time a go & uses Y14.5- 1982 standards. With these drawings, there is clear evidence that callout letters were used twice for two different section views. Additionally, some views have a section view with multiple other section callouts in it, as well as quite a few other isssues. I'm going through the process to try to clean up these drawings & hopefully, at the same time, develop some standards.

I think the best approach is to supercede these drawings with new drawings & I'm assuming with new drawing numbers. However, we still need to track or document changes.

I don't necessarily want to create a huge Was / Is document. Is there a way to provide a generalized document, stating something to the affect:

"Existing drawings does not meet current ASME Y14.5 Standards and was updated with Drawing ###"?

Would something like this be compliant for FAA regulations or do I need to create a Was / Is document?

Thanks

 
Replies continue below

Recommended for you

To make it clear without incident, make it a new part number, delete the old. You may also add a note to the new if you keep the old that it is "similar to" the old part number.

Chris
SolidWorks 10 SP4.0
ctopher's home
SolidWorks Legion
 
Two choices
One, revise old drawing noting supercedded by new drawing. On new drawing, note drawing was updated per ASME Y14.5-2009 and is similar to old drawing.
Two, revise old drawing and just note that it was updated per ASME Y14.5-2009.

Use option 2 if there is no form, fit or function change to the design and you need to maintain the part number for tracking and spares.
Use option 1 if you can use new part numbers and still have tracability.

I assume there is some purpose in cleaning up the old drawing besides just something to do. I worked with modifications on Lockheed P3 aircraft that the original drawings were done on the board and we didb't update the drawings to the latest standards just to make a replacement part.


"Wildfires are dangerous, hard to control, and economically catastrophic."

Ben Loosli
 
There is a way to handle this scenario in the ASME Y14.100 and ASME Y14.35 documents.

The rule is to pull a new number if interchangeability is an issue. If not, it is generally a revision. Some might argue that the interchangeablilty is affected (even if it is not actually changed) by using the new standard and that may require a new number, but that will be up to you.

See ASME Y14.35 fig 2 and paragraph 4.4 for info on to handle this scenario.

Matt Lorono
Lorono's SolidWorks Resources & SolidWorks Legion

http://groups.yahoo.com/group/solidworks & http://twitter.com/fcsuper
 
The above focuses on ASME drawing stds.

I'm not entirely sure what the FAA's take may be. You might want to ask over in one of the aeronautical forums
Posting guidelines faq731-376 (probably not aimed specifically at you)
What is Engineering anyway: faq1088-1484
 
Hi Everyone,

Thanks for the info. I think I have what I need for now.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor