I'm looking for guidance on mitigating water intrusion into underwater cold joints in a marine environment. This is for a pile repair, where the top section will be chipped away and re-poured, leaving a cold joint ~2-4' underwater. I'm specifying a migrating corrosion inhibitor to be added into the mix, but am also wondering if there is a mechanical solution. I'm not certain a water stop would work well as it would be difficult to get a proper seal in the chipped concrete face. Any suggestions?
I'm looking for guidance on mitigating water intrusion into underwater cold joints in a marine environment. This is for a pile repair, where the top section will be chipped away and re-poured, leaving a cold joint ~2-4' underwater. I'm specifying a migrating corrosion inhibitor to be added into the mix, but am also wondering if there is a mechanical solution. I'm not certain a water stop would work well as it would be difficult to get a proper seal in the chipped concrete face. Any suggestions?