Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations TugboatEng on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Step Resource Loading

Status
Not open for further replies.

Smitty38

Mechanical
Joined
Feb 5, 2004
Messages
1
Location
US
Hi everyone, got a question. I use MS Project to schedule all crafts on a construction site. I need to know if, for example: Task -
Install Recycle Line - (Duration 15 days) I want 6 pipefitters for the first 10 days and then reduce to 3 pipefitters for the remaining 5 days.I cannot figure out if Project will allow you to do that on the same task line, or if I have to create a new task, same description and reduce manpower, and naturally link to follow behind the first one requiring 6 people. Hmmmmmm I think I'm confused now!

Thanks!
 
Project primarily deals with level loading.

TTFN
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top