Heavy wheel loads on concrete slab on grade when moving equipment into position during the construction phase.
The local stress at the tire contact area is too high and we need to add steel plate on the floor to distribute the loads.
Does anyone know of any design guides/procedures in determining how thick the plate needs to be in order to achieve the stiffness that makes the assumption of "the load been dispersed/distributed" valid?
Thanks in advance.
The local stress at the tire contact area is too high and we need to add steel plate on the floor to distribute the loads.
Does anyone know of any design guides/procedures in determining how thick the plate needs to be in order to achieve the stiffness that makes the assumption of "the load been dispersed/distributed" valid?