CivilPipe
Civil/Environmental
- May 24, 2011
- 22
I am designing a 40 foot deep reinforced concrete sewage pumping station. The geotechnical boring hit rock at 5' below the surface. I am thinking of allowing the Contractor to backfill the structure with a mixture of select shot rock less than 12-inches and crushed stone up to about 24 inches below the surface and 24 inches of top soil. Should I require filter fabric on top of the shot rock?