boffintech
Civil/Environmental
- Jul 29, 2005
- 469
I'm inspecting on a job right now, high rise CIP concrete, with lots of shearwalls.
One of the shearwall notes reads:
CROSS TIES ARE REQUIRED WHERE AREA OF SCHEDULED VERTICAL REINFORCEMENT
EXCEEDS 0.01 TIMES THE GROSS CONCRETE AREA OF THE WALL. IF CENTER TO
CENTER SPACING OF VERTICAL BARS IS 6" OR SMALLER, CROSS TIES SHALL BE
PLACED AT EVERY OTHER PAIR OF VERTICAL BARS; OTHERWISE, ALL VERTICAL BARS
SHALL BE CONFINED WITH CROSS TIES.
The plan view detail, of course, shows neatly placed #3 cross-ties confining #9 vertical bars; however, in real life there is a 66" lap splice and a #3 bent into a 135-degree hook is never going to wrap around #9's spliced side-by-side.
So I'm curious, out of all the CIP shearwalls I've seen over the years, I've never seen SW verts dog-legged similar to column vertical bars so that the bars can be spliced front-to-back instead of side-to-side.
Is there something in ACI-318 that disallows vertical bars in shearwalls from being dog-legged?
One of the shearwall notes reads:
CROSS TIES ARE REQUIRED WHERE AREA OF SCHEDULED VERTICAL REINFORCEMENT
EXCEEDS 0.01 TIMES THE GROSS CONCRETE AREA OF THE WALL. IF CENTER TO
CENTER SPACING OF VERTICAL BARS IS 6" OR SMALLER, CROSS TIES SHALL BE
PLACED AT EVERY OTHER PAIR OF VERTICAL BARS; OTHERWISE, ALL VERTICAL BARS
SHALL BE CONFINED WITH CROSS TIES.
The plan view detail, of course, shows neatly placed #3 cross-ties confining #9 vertical bars; however, in real life there is a 66" lap splice and a #3 bent into a 135-degree hook is never going to wrap around #9's spliced side-by-side.
So I'm curious, out of all the CIP shearwalls I've seen over the years, I've never seen SW verts dog-legged similar to column vertical bars so that the bars can be spliced front-to-back instead of side-to-side.
Is there something in ACI-318 that disallows vertical bars in shearwalls from being dog-legged?