71corvette
Structural
- Feb 26, 2003
- 105
Hi All,
I’m working on digging up some information regarding the use of shear connectors on steel girder bridges where partial depth precast deck panels are used. Specifically, when shear connectors are used in combination with partial depth precast concrete deck panels, how far do the shear connectors need to project into the CIP portion of the deck slab (if at all)?
AASHTO LRFD requires that shear connectors project a minimum of 2" into the deck slab, but the code is silent on whether the partial depth precast panels count toward this requirement. Separately, PCI New England has a standard detail that requires the shear studs extend at least to the top of the precast deck panel. Other than these two sources, I've been able to dig up only a small amount of guidance on how to approach this issue.
The issue is that having the studs extend up into the CIP portion of the deck slab creates clear cover issues at the top of the stud as haunch height varies. Coversely, not having the studs project into the CIP deck slab creates questions about whether full composite action is being developed.
So, what have your experiences been with this situation? What guidance do your state/local agencies provide when dealing with these situations? I’ve heard some interesting approaches on the topic so far and am interested to hear some of the approaches used by other agencies.
Thanks!
I’m working on digging up some information regarding the use of shear connectors on steel girder bridges where partial depth precast deck panels are used. Specifically, when shear connectors are used in combination with partial depth precast concrete deck panels, how far do the shear connectors need to project into the CIP portion of the deck slab (if at all)?
AASHTO LRFD requires that shear connectors project a minimum of 2" into the deck slab, but the code is silent on whether the partial depth precast panels count toward this requirement. Separately, PCI New England has a standard detail that requires the shear studs extend at least to the top of the precast deck panel. Other than these two sources, I've been able to dig up only a small amount of guidance on how to approach this issue.
The issue is that having the studs extend up into the CIP portion of the deck slab creates clear cover issues at the top of the stud as haunch height varies. Coversely, not having the studs project into the CIP deck slab creates questions about whether full composite action is being developed.
So, what have your experiences been with this situation? What guidance do your state/local agencies provide when dealing with these situations? I’ve heard some interesting approaches on the topic so far and am interested to hear some of the approaches used by other agencies.
Thanks!