nkab38bd
Geotechnical
- Jun 28, 2007
- 1
According to the design, i am to construct some shaft piles with 1.2 m dia penetrating inside very hard rock around 4-5 meter. My contractor is finding difficulties to carry out the boring into hard rock. He is using soilmec SR 60 machine.