sorry no advice on settlement calcs, doubt there will be a problem but sure BigH and Focht3 can give the info. From a construction point of view some railway authorities expect pipes to be cased under railway tracks in case of a burst pipe causing washout. If necessary you can drill the hole to a bigger diameter, say 200mm, and pull in the pipe and casing at the same time.
Zambo