GarthJ
Structural
- Dec 7, 2006
- 10
In a situation where HP piles are required to be driven through a few layers of soil that are not likely to offer a lot of friction resistance and then set onto bedrock. The rock is likely to slope so the piles will have Titus shoes. What setting/refusal criteria should be used? How should the hammer size be established?